House Community
Budget Issue Requests - Tracking Id #141 Town of Sneads Wastewater Treatment Plant Upgrade and Sprayfield Expansion |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Mike Weeks |
Organization: |
Town of Sneads Council |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Town of Sneads Wastewater Treatment Plant Upgrade and Sprayfield Expansion |
Date Submitted: |
01/25/2000 3:17:44 PM |
||||||
|
|
|
|
|
|
|
|
|
|
District Member: |
Bev Kilmer |
Service Area: |
City/Town |
||||||
|
|
|
|
|
|
|
|
|
|
Counties Affected: |
Jackson |
||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Town of Sneads |
Contact: |
William Nobles |
||||||
|
P O Box 159 |
Contact Phone: |
(850) 482-3045 |
||||||
|
|
Sneads 32460 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
The Town of Sneads, Florida desires to upgrade their existing wastewater treatment plant (WWTP) and to expand their effluent sprayfield to bring them into compliance with FDEP regulations. The wastewater treatment and disposal facility serves the Town of Sneads. Through an agreement with the Department of Corrections, the Sneads WWTP also serves the Apalachee Correctional Institute (ACI) located just east of Sneads. The proposed WWTP upgrade will increase the design flow capacity from 0.495 mgd to 1.3mgd, and will increase the effluent sprayfield acreasge from 65 acres to 252 acres. Two 100% capacity (one operating and one installed spare) vertical turbine pumps will provide effluent at 3000 gpm and 86 psig to the sprayfield distribution piping. Each pump will be supplied with a 200 hp TEFC motor. The sprayfield will be divided into 13 zones and will be furnished with solenoid actuated control valves for activating each zone. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Services Provided/Benefit to State: |
|
|
|
|
|
||||
(This project is in the Governor's designated Area of Economic Critical Concern) Resolves a documented recurring water quality violation. It will increase the design flow capacity from 0.495 mgd to 1.3mgd, and will increase the effluent sprayfield acreage from 65 acres to 252 acres. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
The Town of Sneads desires to upgrade its WWTP and expand its effluent sprayfield to bring it into compliance with FDEP regulations, in accordance with Administrative Order No. FLA010115-001. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$2,919,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$7,100,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Is there Local Government or Private match for this request? |
|
Yes |
|
||||||
|
Cash Amount: |
$4,181,000 |
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
Unknown |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
Unknown |
|
||||||
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
FDEP Administrative Order FLA010115-001 |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
City Commissioners Meeting |
|||||||
|
Meeting Date: |
07/14/1998 |
|||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|