Budget Issue Requests - Tracking Id #1936 New Port Richey Reclaimed Water Transmission Main Extensions Phase II |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Thomas O' Neill |
Organization: |
City of New Port Richey |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
New Port Richey Reclaimed Water Transmission Main Extensions Phase II |
Date Submitted: |
01/28/2000 11:03:23 AM |
||||||
|
|
|
|
|
|
|
|
|
|
District Member: |
Mike Fasano |
Service Area: |
City/Town |
||||||
|
|
|
|
|
|
|
|
|
|
Counties Affected: |
Pasco |
||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
City of New Port Richey |
Contact: |
Gerald Seeber |
||||||
|
5919 Main Street |
Contact Phone: |
(727) 841-4500 257 |
||||||
|
|
New Port Richey 34652 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
Approximately 16,860 feet of 8 to 16 inch reclaimed water transmission mains with valves, fittings and associated appurtenances is proposed for interconnection with an existing reclaimed water transmission main network. The project will offset groundwater usage for irrigation in the amount of 250,000 to 500,000 gallons per day. Additionally, by elimination of a WWTP surface water discharge in a like amount, pollutant loadings to an impaired water body (Cross Bayou) will be reduced significantly. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Services Provided/Benefit to State: |
|
|
|
|
|
||||
The end users of the reclaimed water are to be primarily golf courses, public schools, City facilities and parks. Distribution extensions planned in subsequent phases will provide service to residential users. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
The project will offset groundwater ussage for irrigation in the amount of 250,000 to 500,00 gallons per day. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$545,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$1,090,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Is there Local Government or Private match for this request? |
|
Yes |
|
||||||
|
Cash Amount: |
$545,000 |
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
No |
|
||||||
Was this project included in the Governor's Recommended Budget? |
No |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
City of New Port Richey's Master Plan for the Reclaimed Water System |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
New Port Richey City Council |
|||||||
|
Meeting Date: |
10/12/1999 |
|||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|