House Community Budget Issue Requests - Tracking Id #1991

New Port Richey Reclaimed Water Distribution System

 

 

 

 

 

 

 

 

 

 

Requester:

Thomas O' Neill

Organization:

City of New Port Richey

 

 

 

 

 

 

 

 

 

 

Project Title:

New Port Richey Reclaimed Water Distribution System

Date Submitted:

01/28/2000 11:05:53 AM

 

 

 

 

 

 

 

 

 

 

District Member:

Mike Fasano

Service Area:

City/Town

 

 

 

 

 

 

 

 

 

 

Counties Affected:

Pasco

 

 

 

 

 

 

 

 

 

 

Recipient:

City of New Port Richey

Contact:

Gerald Seeber

 

5919 Main Street

Contact Phone:

(727) 841-4536

 

 

New Port Richey 34652

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Project Description:

 

 

 

 

 

 

 

Approximately 12,474 feet of 4 to 12 inch reclaimed water pipeline with valves, fittings and associated appurtenances is proposed for interconnection with a reclaimed water transmission main network under design at this time.  The project will offset groundwater usage for irrigation in the amount of 150,000 to 250,000 gallons per day.  Additionally, by the elimination of a WWTP surface water discharge in a like amount, pollutant loadings to an impaired water body (Cross Bayou) will be reduced significantly.

 

 

 

 

 

 

 

 

 

 

Services Provided/Benefit to State:

 

 

 

 

 

The end users of the reclaimed water are residential single family customers of the City of New Port Richey utility system.

 

 

 

 

 

 

 

 

 

 

Measurable Outcome Anticipated:

 

 

 

 

 

This project will offset groundwater usage for irrigation in the amoount of 150,00 to 250,000 gallons per day.

 

 

 

 

 

 

 

 

 

 

Amount requested from the State for this project this year:

$230,000

 

 

 

 

 

 

 

 

 

 

Total cost of the project:

$460,000

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

Request has been made to fund:

Construction

 

 

 

 

 

 

 

 

 

 

 

 

 

Is there Local Government or Private match for this request?

 

Yes

 

 

Cash Amount:

$230,000

 

 

 

 

 

 

 

 

 

 

 

 

 

Was this project previously funded by the State?

 

No

 

 

 

 

 

 

 

 

 

 

 

Is future-year funding likely to be requested?

 

No

 

 

 

 

 

 

 

 

 

 

 

Was this project included in an Agency's Budget Request?

 

No

 

Was this project included in the Governor's Recommended Budget?

No

 

 

 

 

 

 

 

 

 

 

 

Is there a documented need for this project?

 

Yes

 

 

Documentation:

New Port Richety Capital Improvement Plan

 

 

 

 

 

 

 

 

 

 

Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?

Yes

 

 

Hearing Body:

New Port Richey City Council

 

Meeting Date:

10/12/1999