Budget Issue Requests - Tracking Id #2000 Miami River Dredging Project |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Miami-Dade County Miami-Dade County |
Organization: |
Miami-Dade County |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Miami River Dredging Project |
Date Submitted: |
01/28/2000 4:08:57 PM |
||||||
|
|
|
|
|
|
|
|
|
|
District Member: |
Carlos Lacasa |
Service Area: |
Statewide |
||||||
|
|
|
|
|
|
|
|
|
|
Counties Affected: |
{Statewide} |
||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Miami-Dade County |
Contact: |
Diana Ragbeer |
||||||
|
111 N.W. 1st Street, Suite 2900 |
Contact Phone: |
(305) 375-1257 |
||||||
|
|
Miami 33128 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
The Plan Proposes to dredge the River,dry the sediment near the River, and haul the dried material to a landfill for disposal. Dredging and disposal of the contaminated sediments is expected to enhance the environmental quality of the river and downstream portions of Biscayne Bay and improve navigation. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Services Provided/Benefit to State: |
|
|
|
|
|
||||
Dredging of the River will enhance its environmental quality which wil improve those portions currently being affected by the contaminated sediments. Studies have demonstrated that the contaminated sediments within the River have been carrued into adjoining portions of the Bay: State Aquatic Preserves, SWIM water body, important fishery, and wildlife habitat. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
Upon completion of the project, the navigation channel will be restores to authorize depth and width, allowing enhanced use by freighters and contaminated sediments will no longer be conveyed to Biscayne Bay. Water quality, particularly water clarity, is expected to improve, since sediment resuspension will be reduced following completion of the project. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$4,500,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$81,000,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Operations and Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Is there Local Government or Private match for this request? |
|
Yes |
|
||||||
|
Cash Amount: |
$4,500,000 |
In-Kind Amount: |
$300,000 |
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
Yes |
|
||||||
|
Fiscal Year: |
1999-2000 |
Amount: |
$300,000 |
|
||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
Unknown |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
No |
|
||||||
Was this project included in the Governor's Recommended Budget? |
No |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
The U.S. Army Corps of Engineers determined that dreging is necessary to maintain navigation in 1990 |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
Miami-Dade County Board of County Commissioners Resolution No. R-1360-99. |
|||||||
|
Meeting Date: |
12/16/1999 |
|||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|