Community Budget Issue Requests - Tracking Id #1674 |
Bay County HighPoint and Bollinger Road Improvement Project |
|
Requester: |
Bay County Board of County Com |
Organization: |
Bay County |
|
Project Title: |
Bay County HighPoint and Bollinger Road Improvement Project |
Date Submitted |
1/14/2003 5:19:52 PM |
|
Sponsors: |
Bense |
|
Statewide Interest: |
These roads have been identified by DEP as erosion problems and were included as part of the 61 notice of violations in the Consent order between Bay County Board of County Commissioners and the Department of Environmental Protection. |
|
Recipient: |
John Goin |
|
Contact: |
Josee Cyr |
|
|
310 W. 6th Street |
|
Contact Phone: |
(850) 784-4056 |
|
|
Panama City 32401 |
|
Counties: |
Bay |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The proposed project would include design and construction for road improvements of County Road 2321 in Section 6, T3S, R13W in Bay County |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
Has the project been submitted to the Department of Environmental Protection? |
Yes |
DEP Identfying Number: |
SW20022074 |
|
Measurable Outcome Anticipated: |
The project will correct the erosion problems by providing adequate capacity at the low point crossings, by providing proper end treatment, by stabilizing the roadside swales. The above mentioned measures will reduce erosion and therefore improve the water quality by reducing total suspended solids and contaminates that they carry in Deer Point Lake Reservoir |
|
Amount requested from the State for this project this year: |
$440,000 |
|
Identify item(s) in the FY 2003-04 Appropriations Bill to be reduced: |
|
Specific Appropriation #: |
|
|
Specific Appropriation Title: |
|
|
Amount to be reduced: |
$ |
|
Total cost of the project: |
$480,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$ |
|
In-kind Amount |
$40,000 |
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Executed Consent Order (OGC # 91-1265) |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
No |