Community Budget Issue Requests - Tracking Id #2585 |
Eastern Shores Stormwater Retrofit Phase III |
|
Requester: |
Gary Brown |
Organization: |
City of North Miami Beach |
|
Project Title: |
Eastern Shores Stormwater Retrofit Phase III |
Date Submitted |
1/15/2003 3:03:35 PM |
|
Sponsors: |
Brutus, Roberson |
|
Statewide Interest: |
Completion of the project will accomplish a number of goals that includes protecting public health by reducing water pollutants and improving stormwater management. The Biscayne Bay SWIM Plan has identified Maule Lake as a target water body. Maule Lake is an estuarine lagoon with degraded water quality that provides head water to the lower reach of the Oleta River. This portion of the Oleta River passes through the wetlands of Oleta River State Recreation Area. Constructing an effective stormwater management system would significantly reduce polluntant loadings to these waters used heavily for recreation. In addition during the course of the work, lateral connections will be made to the sanitary sewer for connections that are |
|
Recipient: |
City of North Miami Beach |
|
Contact: |
Shawn Gabriel |
|
|
17050 NE 19th St |
|
Contact Phone: |
(305) 948-2967 |
|
|
North Miami Beach 33163 |
|
Counties: |
Dade |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The purpose of this project is to provide for the retrofitting of the Stormwater infrastructure in a portion of the Eastern Shores Basin located within the City of North Miami Beach. This will include designing and constructing improvements to the existing drainage systems by means of French drains, grease and oil interceptors, grit chambers , and the replacement/refurbishment of stormwater outfalls which discharge into the Maule Lake portion of North Biscayne Bay and Dumfoundling Bay. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
Has the project been submitted to the Department of Environmental Protection? |
Yes |
DEP Identfying Number: |
SW2002096 |
|
Measurable Outcome Anticipated: |
Improved stormwater management. |
|
Amount requested from the State for this project this year: |
$1,200,000 |
|
Identify item(s) in the FY 2003-04 Appropriations Bill to be reduced: |
|
Specific Appropriation #: |
|
|
Specific Appropriation Title: |
|
|
Amount to be reduced: |
$ |
|
Total cost of the project: |
$1,320,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$ |
|
In-kind Amount |
$120,000 |
|
Was this project previously funded by the state? |
|
Yes |
|
Fiscal Year: |
1995-1996 |
Amount: |
$200,000 |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
Unknown |
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Biscayne Bay SWIM Plan |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
Miami-Dade Legislative Delegation |
|
Hearing Meeting Date: |
12/17/2002 |