Community Budget Issue Requests - Tracking Id #3
Lakewood Park Master Pump Station & force Main
 
Requester: Douglas Anderson Organization: St. Lucie County
 
Project Title: Lakewood Park Master Pump Station & force Main Date Submitted 1/14/2003 3:37:16 PM
 
Sponsors: Machek
 
Statewide Interest:
This project wil reduce polluting wastewater that flows into the Indian River Lagoon & the St. Lucie Estuary. Elimination of a small package plant & associated percolation pond that currently operate in this area will reduce the threat of potential loadings to the surficial ground water in the area and the threat of contamination to the public drinking water
 
Recipient: St. Lucie County Board of County Commissioners   Contact: William Blazak  
  2300 Virginia Ave   Contact Phone: (772) 462-1846  
  Ft. Pierce 34982
 
Counties: St. Lucie
 
Gov't Entity: Yes Private Organization (Profit/Not for Profit):  
 
Project Description:
This project includes abandoning the existing Lakewood Park Wastewater Treatment Facility & pumping existing wastewater flows to a regional treatment facility by means of a new six-inch force main, eliminating discharge to the Indian River Lagoon & the St. Lucie Estuary.
 
Is this a water project as described in Chapter 2002-291, Laws of Florida? No
 
Measurable Outcome Anticipated:
Reduced wastewater flow to the Indian River Lagoon & St. Lucie Estuary & reduced ground water contaminations
 
Amount requested from the State for this project this year: $610,000
 
Identify item(s) in the FY 2003-04 Appropriations Bill to be reduced:
 
Specific Appropriation #:  
 
Specific Appropriation Title:  
 
Amount to be reduced: $
 
Total cost of the project: $610,000
 
Request has been made to fund: Construction
 
What type of match exists for this project? None
  Cash Amount $  
 
Was this project previously funded by the state?   No
 
Is future-year funding likely to be requested?   No
 
Was this project included in an Agency's Budget Request?   Yes
  Agency Environmental Regulation, Department Of
 
Was this project included in the Governor's Recommended Budget? Unknown
 
Is there a documented need for this project? Yes
  Documentation: Because of infiltration, inflow & overflow problems; The DEP issued Administrative Order (A097-012-
 
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?   Yes
  Hearing Body: St. Lucie County Board of County Commissioners
  Hearing Meeting Date: 11/12/2002