Community Budget Issue Requests - Tracking Id #474 |
Orange Park Reclaimed Water Transmission Main |
|
Requester: |
Ray O. Avery, Executive Direc |
Organization: |
Clay County Utility Authority |
|
Project Title: |
Orange Park Reclaimed Water Transmission Main |
Date Submitted |
1/14/2003 1:35:34 PM |
|
Sponsors: |
Bean |
|
Statewide Interest: |
This project will protect the environment by removing two point source discharges of secondary treated domestic wastewater treatment plant effuents from a 303d listed impaired water body. These wastewater discharges will be reclaimed and used for beneficial reuse purposes as public access irrigation water in the Clay County Utility Authority's reclaimed water distribution system thereby reducing demand on the Floridan Aquifer and intermediate aquifer groundwater resources. |
|
Recipient: |
Clay County Utility Authority |
|
Contact: |
David Bolam |
|
|
3176 Old Jennings Road |
|
Contact Phone: |
(904) 213-2408 |
|
|
Middleburg 32068 |
|
Counties: |
Clay |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
Design and construction of tertiary and high level disinfection facilities to treat secondary effuent from CCUA's 5.0 MGD Miller Street WWTF and Town of Orange Park's 2.5 MGD WWTF to meet public access reclaimed water standards. Design and Construction of a transfer pumping station and approximately 8.7 miles of 24 inch diameter reclaimed water transmission pipeline. The 24-inch pipeline will deliver the combined flow from CCUA's Miller Street WWTF and the Town of Orange Park's WWTF to CCUA's Spencer's Crossing reclaimed water pumping and distribution facilities. The treatment facilities and transfer pumping station will be located at CCUA's Miller Street WWTF. A separate transmission pipeline approximately 2,500 linear feet long from the Town of Orange Park's WWTF to the Miller Street WWTF will also be required. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
No |
|
Measurable Outcome Anticipated: |
The purposed project will remove pollutant loadings from the St. Johns River by reclaiming the effluent for beneficial reuse purposes. Specifically, we estimate reductions in CBOD5, TSS, TN and TP loadings from both facilities will be 1,126 lbs/day, 1,252 lbs/day, 338 lbs/day, and 211 lbs/day respectfully. Additionally, 7.5 MGD of permitteed wastewater effuent will be removed from the river. |
|
Amount requested from the State for this project this year: |
$3,000,000 |
|
Identify item(s) in the FY 2003-04 Appropriations Bill to be reduced: |
|
Specific Appropriation #: |
|
|
Specific Appropriation Title: |
|
|
Amount to be reduced: |
$ |
|
Total cost of the project: |
$3,000,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$3,686,000 |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
Yes |
|
Amount: |
$7,900,000 |
To Fund: |
Construction |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
1193 Lower St. Johns River SWIM Plan, FDEP's Lower St, Johns River BAsin June 2002 Status Report |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
Clay County Utility Authority Board of Supervisors |
|
Hearing Meeting Date: |
12/17/2002 |