Community Budget Issue Requests - Tracking Id #753 |
SR 528 / SR 15 Interchange Improvements Project |
|
Requester: |
Mayor Glenda Hood |
Organization: |
City of Orlando |
|
Project Title: |
SR 528 / SR 15 Interchange Improvements Project |
Date Submitted |
1/10/2003 5:06:29 PM |
|
Sponsors: |
Allen |
|
Statewide Interest: |
The interchange improvements are necesary to improve conditions at the interchange location and accomodate the eight laning of SR 528 and the four laning of SR 15 to meet regional transpotation needs. Thi s project is located at the Sr 528/ SR15 interchange at the Northeast corner of the Orlando International Airport. These improvements will also improve SR 528's operations as part of the state's hurricaine evacuation system. the project is supported by the Orlando/ Orange Coutny Expressway Authority, the Greater Orlando Aviation Authority, and the Cape Canaveral Port Authority. |
|
Recipient: |
Richard L. Levey, Chief Administative Officer |
|
Contact: |
Kathy Russell |
|
|
400 S. Orange Avenue |
|
Contact Phone: |
(407) 246-3094 |
|
|
Orlando 328024990 |
|
Counties: |
Orange |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The improvements associated with this request approximately 30 miles long and will include structural improvements to SR 528 mainline, SR 15 underpass, includes ramp improvements and will widen SR 15 from its current terminus at SR 528 northward to McCoy Road. The improvement will include re-construction of two-lane roadway to add two travel lanes, sidewalks, transit accomodations and bicycle lanes. The bicycle lanes will connect into the City's 160 miles of existing bikeways. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
No |
|
Measurable Outcome Anticipated: |
Higher per capital income levels, sustained economic vitality, increase in direct/indirect jobs, inproved roadway level of service |
|
Amount requested from the State for this project this year: |
$5,415,254 |
|
Identify item(s) in the FY 2003-04 Appropriations Bill to be reduced: |
|
Specific Appropriation #: |
|
|
Specific Appropriation Title: |
|
|
Amount to be reduced: |
$ |
|
Total cost of the project: |
$5,415,254 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$11,304,000 |
|
|
Was this project previously funded by the state? |
|
Yes |
|
Fiscal Year: |
2002/2003 |
Amount: |
$1,150,000 |
|
Is future-year funding likely to be requested? |
|
Yes |
|
Amount: |
$7,291,621 |
To Fund: |
Construction, Construction, Phase II |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
LRPP, Agency Needs Assesment, ect. |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
No |