Community Budget Issue Requests - Tracking Id #898 |
South Lake Jackson Project near Bellamy Park |
|
Requester: |
City of Maitland |
Organization: |
City of Maitland |
|
Project Title: |
South Lake Jackson Project near Bellamy Park |
Date Submitted |
1/15/2003 3:26:02 PM |
|
Sponsors: |
Mealor, Simmons |
|
Statewide Interest: |
To protect public health and the environment; Project follows the surface water improvement and mgt. act and plan adopted by local governemnt for water quality improvement and restoration. |
|
Recipient: |
City of Maitland |
|
Contact: |
Kim Tracy |
|
|
1776 Independence Lane |
|
Contact Phone: |
(407) 539-6252 |
|
|
Maitland 32751 |
|
Counties: |
Orange |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
Construction of an off-line retention area to treat the stormwater runoof and phosphorous pollution coming from a 79 acre subasin into Lake Sybelia. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
Has the project been submitted to the Department of Environmental Protection? |
Yes |
DEP Identfying Number: |
SW20022148 |
|
Measurable Outcome Anticipated: |
Reduction of stormwater pollution and improvement of lake quality. |
|
Amount requested from the State for this project this year: |
$188,000 |
|
Identify item(s) in the FY 2003-04 Appropriations Bill to be reduced: |
|
Specific Appropriation #: |
|
|
Specific Appropriation Title: |
|
|
Amount to be reduced: |
$ |
|
Total cost of the project: |
$375,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$187,000 |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
Unknown |
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Project is located on the protection area and is part of the city's stormwater/lakes mgt. plan. |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
City Council, City of Maitland |
|
Hearing Meeting Date: |
09/22/2002 |