| Community Budget Issue Requests - Tracking Id #865 | |||||||||
| Hartwood Marsh Road Improvement Phase 1 from two lanes to four lanes | |||||||||
| Requester: | Welton G. Cadwell, Chairman | Organization: | Lake County Board of County Commissioners | ||||||
| Project Title: | Hartwood Marsh Road Improvement Phase 1 from two lanes to four lanes | Date Submitted | 1/13/2003 11:17:58 AM | ||||||
| Sponsors: | Cowin | ||||||||
| Statewide Interest: | |||||||||
| Project will relieve congestion on SR 50 before and after the six lane improvement is completed and will provide an alternate travel route that will include public transportation ITS technology and will also enhance evacuation routes in and out of the Central Florida Region. | |||||||||
| Recipient: | Lake County Board of County Commissioners | Contact: | Noble Olasimbo | ||||||
| 315 W. Main Street | Contact Phone: | (352) 253-4983 | |||||||
| Tavares 32778 | |||||||||
| Counties: | Lake | ||||||||
| Gov't Entity: | Yes | Private Organization (Profit/Not for Profit): | |||||||
| Project Description: | |||||||||
| Adding two lanes as well as rehabilitating the two existing lanes. The improvement will provide an alternate parallel east-west corridor to SR 50 in both Lake and Orange Counties. The extra lanes will provide additional capacities necessary to relieve traffic congestion as well as provide interconnection to SR 50 and US 27. | |||||||||
| Is this a water project as described in Chapter 2002-291, Laws of Florida? | No | ||||||||
| Measurable Outcome Anticipated: | |||||||||
| Fixed Capitol Outlay Economic Development Transportation Project | |||||||||
| Amount requested from the State for this project this year: | $2,567,500 | ||||||||
| Total cost of the project: | $5,135,000 | ||||||||
| Request has been made to fund: | Construction | ||||||||
| What type of match exists for this project? | Local | ||||||||
| Cash Amount | $2,567,000 | ||||||||
| Was this project previously funded by the state? | No | ||||||||
| Is future-year funding likely to be requested? | Unknown | ||||||||
| Was this project included in an Agency's Budget Request? | Unknown | ||||||||
| Was this project included in the Governor's Recommended Budget? | Unknown | ||||||||
| Is there a documented need for this project? | Yes | ||||||||
| Documentation: | 2020 Long Range Transportation Plan | ||||||||
| Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? | Yes | ||||||||
| Hearing Body: | Lake County Legislative Delegation | ||||||||
| Hearing Meeting Date: | 12/04/2002 | ||||||||