| Community Budget Issue Requests - Tracking Id #1932 | |||||||||
| Village of Biscayne Park Flood Protection & Stormwater Management Planning & Implementation | |||||||||
| Requester: | Robert Anderson, Commissioner | Organization: | Village of Biscayne Park | ||||||
| Project Title: | Village of Biscayne Park Flood Protection & Stormwater Management Planning & Implementation | Date Submitted | 1/15/2004 3:11:35 PM | ||||||
| Sponsors: | Margolis | ||||||||
| Statewide Interest: | |||||||||
| Is intended to produce measurable results and to meet a documented need. | |||||||||
| Recipient: | Village of Biscayne Park | Contact: | Joseph Fisher | ||||||
| 640 NE 114 Street | Contact Phone: | (305) 893-4346 | |||||||
| Biscayne Park 33161 | Contact email: | joefisher@bellsouth.net | |||||||
| Counties: | Dade | ||||||||
| Gov't Entity: | Yes | Private Organization (Profit/Not for Profit): | |||||||
| Project Description: | |||||||||
| For the retaining of an engineering firm to assist in the implementation of a stormwater and flood control project (SW20032056) | |||||||||
| Is this a water project as described in Chapter 2002-291, Laws of Florida? | Yes | ||||||||
| Has the project been submitted to the Department of Environmental Protection? | Yes | ||||||||
| DEP Identfying Number: | SW20032056 | ||||||||
| Measurable Outcome Anticipated: | |||||||||
| To better serve the community's need in stormwater & flood control whereby reducing chronic flooding and any environmental deterioration as a result of flooding. In addition the elimination of any public health and safety hazards. | |||||||||
| Amount requested from the State for this project this year: | $100,000 | ||||||||
| Total cost of the project: | $400,000 | ||||||||
| Request has been made to fund: | Operations | ||||||||
| What type of match exists for this project? | None | ||||||||
| Cash Amount | $ | ||||||||
| Was this project previously funded by the state? | No | ||||||||
| Is future-year funding likely to be requested? | Unknown | ||||||||
| Was this project included in an Agency's Budget Request? | No | ||||||||
| Was this project included in the Governor's Recommended Budget? | Unknown | ||||||||
| Is there a documented need for this project? | Yes | ||||||||
| Documentation: | Community outcry & process of applying for PHASE2-MS4 Generic Permit for Discharge of Stormwater app | ||||||||
| Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? | No | ||||||||