| North Pinellas Reclaimed Water Pump Station Rehabilitation | |||||||||
| Requester: | Pinellas County Board of County Commissioners | Organization: | Pinellas County Utilities | ||||||
| Project Title: | North Pinellas Reclaimed Water Pump Station Rehabilitation | Date Submitted | 1/6/2004 11:51:39 AM | ||||||
| Sponsors: | Fasano | ||||||||
| Statewide Interest: | |||||||||
| Optimize the distribution of reclaimed water reducing impacts on groundwater sources while minimizing excess flows to wholesale customers. | |||||||||
| Recipient: | Pinellas County Utilities | Contact: | Elithia V. Stanfield | ||||||
| 14 South Ft. Harrison Ave. | Contact Phone: | (727) 464-3485 | |||||||
| Clearwater 33756 | Contact email: | estanfie@co.pinellas.fl.us | |||||||
| Counties: | Pinellas | ||||||||
| Gov't Entity: | Yes | Private Organization (Profit/Not for Profit): | |||||||
| Project Description: | |||||||||
| Rehabilitation and replacement of obsolete reclaimed water pump station equipment to enhance system performance and improve management of the resource. | |||||||||
| Is this a water project as described in Chapter 2002-291, Laws of Florida? | Yes | ||||||||
| Has the project been submitted to the Department of Environmental Protection? | Yes | ||||||||
| DEP Identfying Number: | WW20032008 | ||||||||
| Measurable Outcome Anticipated: | |||||||||
| Improved utilization of reclaimed water resources and increased power efficiency. | |||||||||
| Amount requested from the State for this project this year: | $350,000 | ||||||||
| Total cost of the project: | $825,000 | ||||||||
| Request has been made to fund: | Construction | ||||||||
| What type of match exists for this project? | Local | ||||||||
| Cash Amount | $475,000 | ||||||||
| Was this project previously funded by the state? | No | ||||||||
| Is future-year funding likely to be requested? | No | ||||||||
| Was this project included in an Agency's Budget Request? | No | ||||||||
| Was this project included in the Governor's Recommended Budget? | No | ||||||||
| Is there a documented need for this project? | Yes | ||||||||
| Documentation: | Pinellas County Reclaimed Water Master Plan | ||||||||
| Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? | Yes | ||||||||
| Hearing Body: | Joint Meeting of Pinellas County Legislative Delegation and Pinellas County Board of County Commissi | ||||||||
| Hearing Meeting Date: | 11/04/2003 | ||||||||