403.507 Preliminary statements of issues, reports,
and studies. ---
(1) Each affected agency identified in paragraph (2)(a) shall
submit a preliminary statement of issues to the department and the applicant
no later than 60 days after the distribution of the complete application. The
failure to raise an issue in this statement shall not preclude the issue from
being raised in the agency's report.
(2)
(a) The following agencies shall prepare reports as provided below
and shall submit them to the department and the applicant within 150 days
after distribution of the complete application:
1. The Department of Community Affairs shall prepare a report
containing recommendations which address the impact upon the public of the
proposed electrical power plant, based on the degree to which the electrical
power plant is consistent with the applicable portions of the state
comprehensive plan and other such matters within its jurisdiction. The
Department of Community Affairs may also comment on the consistency of the
proposed electrical power plant with applicable strategic regional policy
plans or local comprehensive plans and land development regulations.
2. The Public Service Commission shall prepare a report as to the
present and future need for the electrical generating capacity to be supplied
by the proposed electrical power plant. The report shall include the
commission's determination pursuant to s. 403.519 and may include the
commission's comments with respect to any other matters within its
jurisdiction.
3. The water management district shall prepare a report as to
matters within its jurisdiction.
4. Each local government in whose jurisdiction the proposed
electrical power plant is to be located shall prepare a report as to the
consistency of the proposed electrical power plant with all applicable local
ordinances, regulations, standards, or criteria that apply to the proposed
electrical power plant, including adopted local comprehensive plans, land
development regulations, and any applicable local environmental regulations
adopted pursuant to s. 403.182 or by other means.
5. The Game and Fresh Water Fish Commission shall prepare a report
as to matters within its jurisdiction.
6. The regional planning council shall prepare a report containing
recommendations that address the impact upon the public of the proposed
electrical power plant, based on the degree to which the electrical power
plant is consistent with the applicable provisions of the strategic regional
policy plan adopted pursuant to chapter 186 and other matters within its
jurisdiction.
7. Any other agency, if requested by the department, shall also
perform studies or prepare reports as to matters within that agency's
jurisdiction which may potentially be affected by the proposed electrical
power plant.
(b) As needed to verify or supplement the studies made by the
applicant in support of the application, it shall be the duty of the
department to conduct, or contract for, studies of the proposed electrical
power plant and site, including, but not limited to, the following, which
shall be completed no later than 210 days after the complete application is
filed with the department:
1. Cooling system requirements.
2. Construction and operational safeguards.
3. Proximity to transportation systems.
4. Soil and foundation conditions.
5. Impact on suitable present and projected water supplies for this
and other competing uses.
6. Impact on surrounding land uses.
7. Accessibility to transmission corridors.
8. Environmental impacts.
9. Requirements applicable under any federally delegated or approved
permit program.
(c) Each report described in paragraphs (a) and (b) shall contain all
information on variances, exemptions, exceptions, or other relief which may be
required by s. 403.511(2) and any proposed conditions of certification on
matters within the jurisdiction of such agency. For each condition proposed
by an agency in its report, the agency shall list the specific statute, rule,
or ordinance which authorizes the proposed condition.
(d) The agencies shall initiate the activities required by this
section no later than 30 days after the complete application is distributed.
The agencies shall keep the applicant and the department informed as to the
progress of the studies and any issues raised thereby.
(3) No later than 60 days after the application for a federally
required new source review or prevention of significant deterioration permit
for the electrical power plant is complete and sufficient, the department
shall issue its preliminary determination on such permit. Notice of such
determination shall be published as required by the department's rules for
notices of such permits. The department shall receive public comments and
comments from the United States Environmental Protection Agency and other
affected agencies on the preliminary determination as provided for in the
federally approved state implementation plan. The department shall maintain a
record of all comments received and considered in taking action on such
permits. If a petition for an administrative hearing on the department's
preliminary determination is filed by a substantially affected person, that
hearing shall be consolidated with the certification hearing.
(4) The department shall prepare a written analysis, which shall
be filed with the designated hearing officer and served on all parties no
later than 240 days after the complete application is filed with the
department, but no later than 60 days prior to the hearing, and which shall
include:
(a) A statement indicating whether the proposed electrical power
plant and proposed ultimate site capacity will be in compliance with the rules
of the department.
(b) Copies of the studies and reports required by this section and s.
403.519.
(c) The comments received by the department from any other agency or
person.
(d) The recommendation of the department as to the disposition of the
application, of variances, exemptions, exceptions, or other relief identified
by any party, and of any proposed conditions of certification which the
department believes should be imposed.
(e) The recommendation of the department regarding the issuance of
any license required pursuant to a federally delegated or approved permit
program.
(f) Copies of the department's draft of the operation permit for a
major source of air pollution, which must also be provided to the United
States Environmental Protection Agency for review within 5 days after issuance
of the written analysis.
(5) Except when good cause is shown, the failure of any agency to
submit a preliminary statement of issues or a report, or to submit its
preliminary statement of issues or report within the allowed time, shall not
be grounds for the alteration of any time limitation in this act. Neither the
failure to submit a preliminary statement of issues or a report nor the
inadequacy of the preliminary statement of issues or report shall be grounds
to deny or condition certification.
History: s. 1, ch. 73-33; s. 5, ch. 76-76; s. 133, ch. 79-190; s. 8, ch. 81-131;
s. 33, ch. 81-169; s. 36, ch. 83-55; s. 25, ch. 86-186; s. 10, ch. 90-331; s.
7, ch. 92-132; s. 8, ch. 93-94; s. 385, ch. 94-356; s. 14, ch.
95-149.