216.043 Budgets for fixed
capital outlay. ---
(1) A legislative budget request, reflecting the
independent judgment of the head of the agency or of the Chief
Justice of the Supreme Court with respect to the needs of the
agency or of the judicial branch for fixed capital outlay during
the next fiscal year, shall be submitted by each head of an agency
and by the Chief Justice and shall contain:
(a) An estimate in itemized form showing the amounts
needed for fixed capital outlay expenditures, to include a detailed
statement of program needs, estimated construction costs and
square footage, site costs, operating capital necessary to furnish
and equip for operating a new or improved facility, and the
anticipated sources of funding during the next fiscal year.
(b) Proposed fixed capital outlay projects, including
proposed operational standards related to programs and utilization,
an analysis of continuing operating costs, and such other data as
the Executive Office of the Governor deems necessary for state
agencies, or the Chief Justice deems necessary for the judicial
branch, to analyze the relationship of agency needs and program
requirements to construction requirements. The plan shall also
include the availability and suitability of privately constructed
and owned buildings and facilities to meet the needs and program
requirements of the agency or of the judicial branch.
(c) For any budget request for fixed capital outlay or
operating capital outlay which is to be funded by a proposed state
debt or obligation as defined in s. 216.0442, the information set
forth in s. 216.0442(2).
(2) The legislative budget requests for fixed capital
outlay shall be submitted as a product of an ongoing planning
process which:
(a) Relates to program plans in an anticipatory manner so
as to identify facility requirements sufficiently early to provide
lead time for planning and construction without deterring the
operation of the applicable program.
(b) Applies that lead time to the budget
process.
(3) Each legislative budget request for fixed capital
outlay submitted shall contain:
(a) A schedule of projects planned to meet the 4-year
requirements of the agency or of the judicial branch and a schedule
of anticipated funding for the initial fiscal year of the 4-year
period.
(b) A full explanation of the basis for each project,
including a description of the program which requires the facility;
an explanation of the inability of existing facilities to meet
such requirements; historical background; alternatives; and
anticipated changes in operating costs, both initial and
continuing.
(c) An application of standards and criteria to establish
the scope of each project.
(d) An application of cost factors to all elements of each
project to establish an estimate of funding requirements.
(e) A request for legislative appropriation to provide
such funding in the appropriate fiscal year, including the need for
advance funding of programming and design activities.
(f) A priority list of fixed capital outlay projects for
which the construction of the project may be deferred for
countercyclical purposes for a period not to exceed 12
months.
History: s. 31, ch. 69-106; s. 1, ch. 75-243; s. 5, ch. 77-352; s. 4,
ch. 80-45; s. 6, ch. 83-49; s. 6, ch. 91-109; s. 40, ch.
92-142.